Filters
Question type

Study Flashcards

Scheduling in service systems may involve scheduling: (I) the workforce. (II) the equipment. (III) customers.


A) II only
B) I and II only
C) II and III only
D) I and III only
E) I, II, and III

F) D) and E)
G) B) and E)

Correct Answer

verifed

verified

E

Organizations with fixed, perishable capacity can benefit from:


A) yield management.
B) price increases.
C) constraints.
D) suboptimization.
E) waiting lines.

F) B) and D)
G) All of the above

Correct Answer

verifed

verified

Priority rules are widely used to sequence jobs in high-volume systems.

A) True
B) False

Correct Answer

verifed

verified

The scheduling sequencing rule which always results in the lowest average completion (flow) time is the:


A) first come, first served (FCFS) rule.
B) shortest processing time first (SPT) rule.
C) earliest due date first (EDD) rule.
D) least slack per operation first (S/O) rule.
E) run until slack happens (RUSH) rule.

F) A) and D)
G) A) and C)

Correct Answer

verifed

verified

B

The costs to do each of the three jobs on three alternate pieces of equipment are given below. Determine the job-equipment combination that will minimize total cost.  Job ABC Crew 1$28201822622143433530\begin{array}{ c}\quad\quad\quad\text { Job }\\\begin{array}{rcc}&\mathrm{A} & \mathrm{B} & \mathrm{C} \\\hline\text { Crew }1& \$ 28 & 20 & 18\\2&26 & 22 & 14 \\3&43 & 35 & 30\end{array}\end{array}

Correct Answer

verifed

verified

blured image_TB2513_00_TB2513_00
\[\begin{array}{l ...

View Answer

The president of a consulting firm wants to minimize the total number of hours it will take to complete four projects for a new client. Accordingly, she has estimated the time it should take for each of her top consultants-Charlie, Betty, Johnny, and Rick-to complete any of the four projects, as follows:  Project (Hours)   Consultant  A  B  C  D  Charlie 13161113 Betty 11151418 Johnny 15221215 Rick 17171222\begin{array} { c } \quad \quad \quad \quad \quad { \text { Project (Hours) } } \\\begin{array} { l c c c c } \text { Consultant } & \text { A } & \text { B } & \text { C } & \text { D } \\\hline \text { Charlie } & 13 & 16 & 11 & 13 \\\text { Betty } & 11 & 15 & 14 & 18 \\\text { Johnny } & 15 & 22 & 12 & 15 \\\text { Rick } & 17 & 17 & 12 & 22\end{array}\end{array} What is the optimal assignment of consultants to projects?


A) Charlie to A; Betty to B; Johnny to C; Rick to D
B) Charlie to D; Betty to C; Johnny to B; Rick to A
C) Charlie to C; Betty to A; Johnny to D; Rick to B
D) Charlie to D; Betty to B; Johnny to C; Rick to A
E) Charlie to D; Betty to A; Johnny to C; Rick to B

F) B) and C)
G) A) and E)

Correct Answer

verifed

verified

There are four resources and four jobs to be done. The time required for each resource to do each job is as follows:  Job (Hours)   Resource ABCD15877249593698747669\begin{array} { c } \quad \quad \quad \quad { \text { Job (Hours) } } \\\begin{array} { l c c c c } \text { Resource } & \mathrm { A } & \mathrm { B } & \mathrm { C } & \mathrm { D } \\\hline 1 & 5 & 8 & 7 & 7 \\2 & 4 & 9 & 5 & 9 \\3 & 6 & 9 & 8 & 7 \\4 & 7 & 6 & 6 & 9\end{array}\end{array} For the optimal schedule, what is the total number of hours required to complete these jobs?


A) 23 hours
B) 22 hours
C) 21 hours
D) 20 hours
E) 19 hours

F) C) and D)
G) B) and C)

Correct Answer

verifed

verified

Line balancing is a major factor in the design and scheduling of low-volume systems because of batch processing.

A) True
B) False

Correct Answer

verifed

verified

Splitting a large lot after one operation beyond a bottleneck operation would reduce the overall waiting time of the bottleneck operation.

A) True
B) False

Correct Answer

verifed

verified

The owner/operator of the local franchise of Handyman, Inc., has four jobs to do today, shown in the order they were received:  Job  Processing  Time (hrs)   Due  (hrs from now)   W 44X35Y22Z11\begin{array} { l c c } \text { Job } & \begin{array} { c } \text { Processing } \\\text { Time (hrs) }\end{array} & \begin{array} { c } \text { Due } \\\text { (hrs from now) }\end{array} \\\hline \text { W } & 4 & 4 \\\mathrm { X } & 3 & 5 \\\mathrm { Y } & 2 & 2 \\\mathrm { Z } & 1 & 1\end{array} If he uses the first come, first served priority rule to schedule these jobs, what will be the average completion time?


A) 7.5 hours
B) 5 hours
C) 3 hours
D) 2.5 hours
E) 2 hours

F) A) and E)
G) C) and D)

Correct Answer

verifed

verified

Average completion (flow) time for a schedule sequence at a work center is:


A) the sum of processing time divided by the number of jobs.
B) the sum of jobs' flow times divided by the number of jobs.
C) overall flow time divided by total processing time.
D) total processing time plus total late time divided by number of jobs.
E) the sum of flow time plus total late time divided by number of jobs.

F) B) and E)
G) A) and E)

Correct Answer

verifed

verified

Given the following data for jobs awaiting processing at a manufacturing cell in which jobs are first processed by machine A, then by machine B:  Process Time (Hours)  Job  Center A  Center B W45X66Y12Z52\begin{array} { c } \quad\quad\quad{ \text { Process Time (Hours) } } \\\begin{array} { l c c } \text { Job } & \text { Center A } & \text { Center B } \\\hline \mathrm { W } & 4 & 5 \\\mathrm { X } & 6 & 6 \\\mathrm { Y } & 1 & 2 \\\mathrm { Z } & 5 & 2\end{array}\end{array} If these jobs were scheduled in the sequence shown, what would be the idle time at machine B?

Correct Answer

verifed

verified

In an assignment method problem, if it takes Abe 3 hours to build a birdhouse and 4 hours for a doghouse, while Betty takes 4 hours for a birdhouse and 3 hours for a doghouse, what is the reduced cost (in hours) of assigning Abe to build the doghouse?


A) 0 hours
B) 1 hour
C) 2 hours
D) 3 hours
E) 4 hours

F) A) and D)
G) A) and C)

Correct Answer

verifed

verified

B

The operations manager of a body and paint shop has five cars to schedule for repair. He would like to minimize the throughput time to complete all work on these cars. Each car requires body work prior to painting. The estimates of the times required to do the body paint work on each are as follows:  Car  Body Work  (hrs)   Paint  (hrs)   A 102 B 54 C 75 D 36 E 17\begin{array} { l c c } \text { Car } & \begin{array} { c } \text { Body Work } \\\text { (hrs) }\end{array} & \begin{array} { c } \text { Paint } \\\text { (hrs) }\end{array} \\\hline \text { A } & 10 & 2 \\\text { B } & 5 & 4 \\\text { C } & 7 & 5 \\\text { D } & 3 & 6 \\\text { E } & 1 & 7\end{array} Where in the optimum sequence should car E be scheduled?


A) first
B) second
C) third
D) fourth
E) fifth

F) All of the above
G) None of the above

Correct Answer

verifed

verified

The assignment model seeks an optimum matching of tasks and resources.

A) True
B) False

Correct Answer

verifed

verified

There are three jobs to be done and three resources with which to do them. Each resource will take a specific time to do each job, as shown in the following table:  Machine  Job  A  B  C 169424433874\begin{array} { c } { \text { Machine } } \\\begin{array} { l c c c } \text { Job } & \text { A } & \text { B } & \text { C } \\\hline 1 & 6 & 9 & 4 \\2 & 4 & 4 & 3 \\3 & 8 & 7 & 4\end{array}\end{array} What is the result of the row and column reductions?

Correct Answer

verifed

verified

\[\begin{array} { | c | c | c ...

View Answer

There are three jobs to be done and three resources with which to do them. Each resource will cost a specific amount to do each job, as shown in the following table:  Machine  Job  A  B  C 1$69424433874\begin{array} { l c c c } & &{ \text { Machine } } \\\text { Job } & \text { A } & \text { B } & \text { C } \\\hline 1 & \$ 6 & 9 & 4 \\2 & 4 & 4 & 3 \\3 & 8 & 7 & 4\end{array} What is the optimum assignment of jobs to machines?

Correct Answer

verifed

verified

1 to A; 2 ...

View Answer

Refer to the following data for jobs waiting to be processed at a single work center (jobs are shown in order of arrival):  Job  Processing Time ( days ) Due Date  (days from now) A22 B56C610D34E48\begin{array} { l c c } \text { Job } & \begin{array} { c } \text { Processing Time } \\( \text { days } )\end{array} & \begin{array} { c } \text { Due Date } \\\text { (days from now) }\end{array} \\\hline \mathrm { A } & 2 & 2 \\\mathrm {~B} & 5 & 6 \\\mathrm { C } & 6 & 10 \\\mathrm { D } & 3 & 4 \\\mathrm { E } & 4 & 8\end{array} What is the average completion time for the slack per operation (S/O) priority rule schedule? Average job tardiness? Average number of jobs at the center?

Correct Answer

verifed

verified

11 days; 5...

View Answer

Flow-shop scheduling is used in high-volume systems.

A) True
B) False

Correct Answer

verifed

verified

A schedule chart depicts the loading and idle times for a group of machines or departments.

A) True
B) False

Correct Answer

verifed

verified

Showing 1 - 20 of 134

Related Exams

Show Answer